Sl. No
|
Project
|
Firm’s Name
|
P.O. No. / LoA No. & DP
|
Order
Qty.
|
Status
|
6.
|
Up gradation of WAG-9H locomotive to 9000 HP
|
Siemens
|
P.O.No.70/18/1145/01152
dated: 04.12.2017
Original DP-As per the modalities given in the clause no 3.0 of scc as per clw spec.
|
5 sets
|
Approval of Preliminary design concept of 9000 HP Freight Locomotive done in May’2018.
Firm submitted detailed design concept under stage II.
· Discussion held with firm regarding discrepancies found in stage-II documentation. Power cable layout scheme done by CLW.
· Provisional approval of design document accorded for integrated converter, VCU and cable layout scheme.
· Procurement of 01 no of shell assembly from M/s Chandra Udyog accorded.
|
Amendment No. 1 (One)of P.O.No.70/18/1145/01152dated: 04.12.2017 for supply and commissioning of upgradation kit for Passenger Locomotives (Vide L/ No. 70/18/1145(GT) dated. 03.01.2018).
|
5 sets
|
Supply yet to commence
|
Medha
|
P.O.No.70/18/1145/01220
dated: 12.04.2018.
Original DP- As per the modalities given in the clause no 3.0 of scc as per clw spec. No. CLW/C-D7D/0549/SCC ALT. 0
|
2 sets
|
Preliminary design clearance granted.
Detailed design submitted on 11/09/18.
Approval of Stage-II design documents & test protocol of Traction converter, Auxiliary converter.
|
BHEL
|
P.O.No.70/18/1145/01226
dated: 12.04.2018.
Original DP- As per the modalities given in the clause no 3.0 of scc as per clw spec. No. CLW/C-D7D/0549/SCC ALT. 0
|
1 set
|
Validation of Bogie done at BHEL/JHANSI.
Design calculation for TE/BE submitted.
Under scrutiny at CLW.
|
7.
|
Provision of Crew voice & video recording system on 3-ph passenger locomotives.
As per Specn No.
RDSO/2015/EL/SPEC/0118 [Rev ’0’].
|
Trolex
|
P.O. No. 34/2017/2972/ 38096 dated: 21.08.2017.
Prototype unit:Prototype 03 months from the date of P. O.
Series Supply:Remaining sets within 06 months from prototype inspection i.e by 31.05.2018.
|
10 sets
|
Prototype
Unit commissioned in loco no. 32150 at ELS/GMO.
|
Kayson
|
P.O issued.
|
5 sets
|
First unit commissioned in loco No. 32101.
2nd unit commissioned in loco no. 30164.
|
Elixir
|
P.O issued.
|
3 sets
|
Firm to submit Design document.
|
8.
|
Group-IGBT based 3-Phase Drive Propulsion Equipment along with Control Cubicle SB-1 & SB-2(Excluding Control Electronics)
|
BTIPL
|
P.O. No. 70/18/1147/11361 dated: 22.05.2018.
Original DP- To commence within 3-4 months from the date of orderor as early as possble @ 8-10 sets/month.To be completed by 15.02.2019
|
42
sets
|
08 sets received at CLW.
06 nos. are in transit.
|
MEDHA
|
P.O. No. 70/18/1147/11364 dated: 06.06.2018.
Original DP- To commence within 4 months from the date of order or as early as possble @ 10 sets/month.(04+02 months)
|
12 sets
|
Supply yet to commence.
|
ABB
|
P.O. No. 70/18/1147/11363 dated: 06.06.2018.
Original DP- To commence within 4 months from the date of order or as early as possble @ 10 sets/month.(04+02 months)
|
18 sets
|
Supply yet to commence.
|
|
BHEL
|
P.O. No. 70/18/1147/11377 dated: 04.07.2018.
Original DP- To commence within 4 months from the date of order or as early as possble @ 10 sets/month.(04+03months)
|
28
sets
|
Supply yet to commence.
|
9.
|
Development of Alternate Gear drives Assembly for WAP5 AC Electric Locomotives (200 Kmph)
(Rly. Bd’s L/No. 2007/Elect (TRS)/440/15 dated: 26.02.09).
|
M/s Arihant Electricals
Kol.
|
P.O. No. 91/10/0945/NS/ 00135 dated: 09/06/10
Original DP:
Prototype unit: 1 loco set within 06 months from PO.
Series Supply:
After 03 months from successful clearance of prototype for 06 months.
Extended DP: upto 31.3.14
|
2 sets
|
Prototype unit commissioned on loco No. 30086. Loco dispatched to ELS/GZB in Oct’15.
2nd unit commissioned in loco no. 30164 at CLW and sent to ELS/GZB in October’18.
|
10.
|
Development of Alternate Gear drives Assembly for WAP5 AC Electric Locomotives (160 Kmph).
|
M/s Arihant Electricals
Kol.
|
P.O. No. 91/10/0943/ 00096 dt.12/03/2010
Original DP: Prototype unit: 05 Nos. within 06 months from PO.
Series Supply: After 03 months from successful clearance of prototype for 18 months.
Extended DP: DP extended upto 31.3.15.
|
05 sets
|
Prototype unit commissioned in Loco No. 30056. Loco under commercial service since Dec’12 under ELS/BRCY.
2nd, 3rd and 4th set commissioned on loco No. 30087, 30090& 30100 and sent to ELS/BRCY in Nov’15 & Jan’16 and ELS/GZB in March’16 respectively.
Supply of 03 Nos. yet to commence.
|
Tender for 20 loco sets opened on 31.05.2017.
P.O issued against 3 firms.
- M/s Involute Technologies-10 sets
- M/s Mackeil and Compant Pvt. Ltd.-04 sets
- M/s River Engineering (counter offer)- 06 sets
|
11.
|
Vehicle Control Unit based on TCN open standard for 3-phase locomotives as per CLW specification No. CLW/C_D&D/ ES/3/TCN/0547 Dated: May’2016.
|
M/s ABB
|
P.O. No. 70/16/1142/ 11003 dated: 07.03.2017.
Original DP:
Prototype unit: Within 03 months from PO.
Series Supply: After 03 months from date of clearance of prototype.
P.O. to be completed by 31.03.2018.
|
02 sets
+02 sets
|
All sets received at CLW.
|
P.O. No. 70/18/1142/ 11195 dated: 15.09.2017.
Delivery: 10 sets by October 2017.Balance @10 sets per month
TDP- January 2018
|
44 sets
|
All sets received at CLW.
|
P.O. No. 70/18/1142/01/ 11286 dated: 27.11.2017.
DP: To supply as early as possible and to be completed by Feb’18.
TDP- 28.02.2018.
|
13 sets
|
All sets received at CLW.
|
M/s BHEL
|
P.O. No. 70/16/1142/ 11002 dated: 07.03.2017.
Original DP:
Prototype unit: Within 03 months from PO.
Series Supply: After 03 months from date of clearance of prototype. P.O. to be completed by 31.03.2018.
|
03 sets
To be increased to 06 sets
|
One set received at CLW.
Prototype and routine test protocol approved for remaining sets.
|
P.O. No. 70/17/1142/ 11077 dated: 17.06.2017
Prototype unit: Within 06 months from PO.
Series Supply: 12 sets per quarter thereafter.
|
42 sets
|
Supply yet to commence.
|
P.O. No. 70/18/1142/ 11230 dated: 09.10.2017
DP: To start within 03 months from date of P.O. @05 sets per month, to be completed by 31.03.2018.
|
23 sets
|
Supply yet to commence.
|
M/s CGL
|
P.O. No. 70/16/1142/ 11003 dated: 07.03.2017.
Original DP:
Prototype unit: Within 03 months from PO.
Series Supply: After 03 months from date of clearance of prototype.
P.O. to be completed by 31.03.2018.
|
05 sets
to be increased to 10 sets
|
All sets received at CLW.
|
P.O. No. 70/17/1142/ 11078 dated: 17.06.2017
DP: To commence from 01.04.2018 and would be completed by 31.12.2018.
|
28 sets
|
All sets received at CLW.
|
|
|
P.O. No. 70/18/1142/01/ 11287 dated: 27.11.2017.
DP: To supply as early as possible and to be completed by January’18.
|
12 sets
|
All sets received at CLW.
|
|
M/s AAL
|
P.O. No. 70/16/1142/ 11008 dated: 14.08.2018.
DP: To be completed by 31.03.2019
|
02 sets
|
Supply yet to commence.
|
12.
|
Remote Monitoring System for 3-phase Electric Locomotives (Specification No.
C-D&D/ES/3/0546)
|
M/s ARC
|
P.O.No.
72/16/1268(NS)/11321
Dated: 31.01.2018
DP:To be completed within 06 monthsfrom the date of Prototype clearance.
|
54 sets
|
Prototype unit commissioned in loco no 30715 and loco dispatched to ELS/GZB.
|
M/s Lotus
|
P.O.No. 72/16/1268(NS)/11320
Dated: 31.01.2018
DP:To be completed within 06 monthsfrom the date of Prototype clearance.
|
83 sets
|
Commissioned in loco no. 32165 and sent to ELS/BIA.
|
13.
|
Development of Distributed Power Wireless Control System (DPWCS)for 3-phase electric loco. (P.B. item No. 37/ 2012-13.) Rly. Bd’s L/No. 2003/ Elect (TRS)/441 /8 dt. 29.12.06)
P.B. item no. 358/2012-13, 1122/2012-13.
|
M/s. ARC/
B’lore
|
LoA No. OT/ C-D&D/01/07/ 2007-08 dated 3rd June, 2008.
|
2 pair of locos
|
The prototype pairs have been installed in loco nos. 31282 (WAG-9) & 31284 (WAG-9). Loco has been put into commercial service w.e.f. 18.05.2012.
2nd set has been installed on Loco No. 31525 & 31526 and dispatched to ELS/TATA in Nov.’14.
|
P.O. No. 70/16/1140/01088 dated: 28.06.2017.
Original DP:
Prototype unit: Within 06 months from PO.
Series Supply: @ 10 sets /month.
|
45 sets
|
30 sets received at CLW.
18 sets lying at CLW.
First set commissioned in loco no. 32101 & 32019 at ELS/KZJ,
1 set commissioned at ELS/BRC in loco no 30087 & 30090,
Another 10 sets commissioned at ELS/TATA .
Further 04 sets spared to ELS/GMO against RSP
|
GE
|
P.O. No. 70/16/1140/01090 dated: 28.06.2017.
Prototype unit: Within 06 months from PO.
Series Supply: Within 06th month of prototype clearance and to be completed by 12 months after issuance of P.O.
|
10 sets
|
Design document under scrutiny.
|
Lotus
|
P.O. No. 70/16/1140/01089 dated: 28.06.2017.
Prototype unit: Within 06 months from the date of P.O. delivery.
Series Supply: @ 10 sets /month from 6th month of prototype clearance
|
20 sets
|
Design Document got approved.
Prototype inspection has been done.
Commissioned in loco no. 32196 & 31879 at VSKP.
|
14.
|
Fault Diagnostic Tool for 3- phase Locomotives as per Specn./Drg. No. CLW/C-D&D/ES/3/0545 Aemendment-1 issued in August 2014.
|
BTIPL
|
P.O. No. 91/17/1007/ 01229 dated: 06.03.2018.
Delivery Period: Within 10 months from the date of PO.
|
40 sets
|
All sets received at CLW. Distributed to sheds against RSP.
|
ARC
|
P.O. No. 91/17/1007/ 01228 dated: 06.03.2018.
Delivery Period: prototype Within 06 months and delivery to be completed within 03 months of clearance of prototype.
|
10 sets
|
First prototype unit supplied. Remaining units to be supplied.
|
15.
|
IGBT based Composite Converter with Traction Converter and Hotel Load Converter for 3-ph WAP-5 locomotives as per Specification No. CLW/ES/IGBT/ 0518 Alt. B
|
ABB
|
P.O. No. 70/16/1136/ 10994 dated: 25.02.2017.
Original DP:
Prototype unit: Within 10 months from PO.
Series Supply: After 06 months from date of clearance of prototype.
|
10 sets
|
First unit Commissioned in Loco no. 30140 in June’18.
Second unit commissioned in WAP-7 loco no 30715 in October’18.
|
CGL
|
P.O. No. 70/16/1136/ 11016 dated: 23.03.2017.
Original DP:
Prototype unit: Within 12 months from PO.
Series Supply: After 03 months from date of clearance of prototype @ 3 sets /quarter.
|
05 sets
|
Firm has been advised to incorporate critical design features for further scrutiny.
|
BHEL
|
P.O. No. 70/16/1136/ 10995 dated: 25.02.2017.
Original DP:
Prototype unit: Within 12 months from PO.
Series Supply: After clearance of prototype @ 2 sets /quarter.
|
05 sets
|
Design document submitted.
BOM, OGA drawing.
And Type test protocol approved.
|